Timeline
2001 | Hutt River Floodplain Management Plan |
2009 | Hutt City Council ‘Making Places’ concepts |
2012 | Greater Wellington flood protection option development |
2014 | Melling Gateway Strategic Case |
2015 | Greater Wellington flood protection option selected |
2016 | SH2 Programme Business Case - Ngauranga to Te Marua |
2017 | Preliminary design; NZTA Melling intersection Indicative Business Case |
2019 | NZTA Melling Transport Improvements Single Stage Business Case |
2019–2021 | Pre-implementation planning and design; community engagement; business case |
2021 | Project resource consent lodged on 25 August 2021 |
2022 | Resource consent approved; design and construction Alliance contract preparation and award |
May 2023 | Establishment of Te Wai Takamori o Te Awa Kairangi - Delivering RiverLink Alliance |
June 2023 - June 2024 | Confirming scope and reviewing the Reference Design |
July 2023 - June 2024 | Undertaking ground investigations, property removal, locating utilities and pavement investigations |
October 2023 | Start developing detailed design for early works i.e. Mills Street stopbank |
February 2024 | Commence early works, including site establishment, Mills St stopbank |
2024-2025 | Detailed design for the main construction works |
2024 onwards | Commence main construction works |
2028 | Expected construction finish |