Timeline
2001 | Hutt River Floodplain Management Plan |
2009 | Hutt City Council ‘Making Places’ concepts |
2012 | Greater Wellington flood protection option development |
2015 | Greater Wellington flood protection option selected |
2017 | Preliminary design; Waka Kotahi Melling intersection indicative business case |
2019 | Waka Kotahi Melling transport improvements detailed business case |
2019–2021 | Pre-implementation planning and design; community engagement; business case |
2021 | Project resource consent lodged on 25 August 2021 |
2022 | Resource consent approved; design and construction contract awarded; detail design starts |
May 2023 | Establishment of Te Wai Takamori o Te Awa Kairangi Alliance - Delivering RiverLink |
June - October 2023 | Confirming scope and reviewing the Reference Design |
July 2023 - March 2024 | Undertaking ground investigations and property removal |
July 2023 | Start developing detailed design for early works i.e. Mills Street stop bank |
November 2023 - April 2025 | Detailed Design |
Late 2023 | River and stop bank construction commences |
2024 | Commence interchange and footbridge construction |
2028 | Complete construction |